A and B work together to complete a task in 6 days. If A can finish the task alone in 9 days, how many days would B take to complete the task alone?
A. 20 days
B. 18 days
C. 24 days
D. 28 days
Correct Answer: B (18 days)
» Read More…
A. 20 days
B. 18 days
C. 24 days
D. 28 days